Since many new processing plants install state-of-the-art control systems such as DeltaVTM, commissioning and startup include such activities as:

  • Check hardware, including wiring, to ensure that each motor starts from the correct motor control center (MCC)
  • Check software addressing to ensure each motor & instrument responds from the correct icon on the display
  • Start all pieces of equipment
  • Check power supply & functionality
  • Check safety & software interlock sequences using
    • PEHTC, written documentation and/or
    • Client-written documentation reviewed by PEHTC
  • Perform system trial runs with water or sacrificial product
  • Tune process control loops, such as temperature, pressure, flow
  • Train operators
  • Perform turn-over